If contractors and suppliers don鈥檛 get paid on a construction project in North Carolina, they can file a mechanics lien to secure payment. A mechanics lien is a legal tool that provides the unpaid party with a security interest in the property. This page breaks down the rules, requirements, and deadlines you need to follow to file a North Carolina mechanics lien.

Quicklinks

“麻豆tv大片 takes something that is pretty complex and makes it easy.”

Ready to file a lien in North Carolina?

North Carolina lien law deadlines for:

Preliminary notice deadlines
15 days

Notice to Lien Agent required within 15 days from first furnishing labor and/or materials.

Mechanics lien deadlines
120 days

Lien filed and served within 120 days from last furnishing labor or materials.

Enforcement deadlines
180 days

An action to enforce a North Carolina mechanics lien must be initiated within 180 days after the claimant's last furnishing of labor or materials.

Note that this deadline runs from last furnishing, so it is possible that the deadline could be as short as 60 days from the filing of the lien itself. This deadline may not be extended, and missing the deadline invalidates the lien.

Preliminary notice deadlines
15 days

Notice to Lien Agent required within 15 days from first furnishing labor and/or materials. Notice of Subcontract if Notice of Contract Filed by Prime Contractor.

Mechanics lien deadlines
120 days

Lien filed and served within 120 days from last furnishing labor or materials.

Enforcement deadlines
180 days

An action to enforce a North Carolina mechanics lien must be initiated within 180 days after the claimant's last furnishing of labor or materials.

Note that this deadline runs from last furnishing, so it is possible that the deadline could be as short as 60 days from the filing of the lien itself. This deadline may not be extended, and missing the deadline invalidates the lien.

Preliminary notice deadlines
15 days

Notice to Lien Agent required within 15 days from first furnishing labor and/or materials. Notice of Subcontract if Notice of Contract Filed by Prime Contractor.

Mechanics lien deadlines
120 days

Lien filed and served within 120 days from last furnishing labor or materials.

Enforcement deadlines
180 days

An action to enforce a North Carolina mechanics lien must be initiated within 180 days after the claimant's last furnishing of labor or materials.

Note that this deadline runs from last furnishing, so it is possible that the deadline could be as short as 60 days from the filing of the lien itself. This deadline may not be extended, and missing the deadline invalidates the lien.